AI translation of the original report. Names and wording may contain translation errors. Read the original text
Barnaul City Hospital No. 5 recovered more than 2 million rubles from a contractor.
The company “Babylon” carried out renovations at the medical facility. The contractor was supposed to provide a five-year warranty on the work performed and secure it with an amount of 2.1 million rubles. The renovation was completed, accepted, and paid for. However, according to court documents, “Babylon” did not provide the guarantee for the work performed.
“The warranty period for work performed under the contract is at least five years from the date the acceptance document is signed; for materials, structures, and products installed during the work, it is at least 12 months. The amount securing the warranty obligations is 2,140,000 rubles,” the case materials state.
During the trial, the defendant said it could not make the payment because its accounts were blocked. However, the court ruled in favor of the plaintiff. “Babylon” must now pay the hospital 2.1 million rubles. The contractor was also ordered to reimburse 50,000 rubles in state duty expenses.
👍 TOLK | TOLK on MAX